Solar Panels

Solar Panel Installation UK: What to Expect on the Day

By James Crawford | 2025-10-25 | 14 min read
Solar Panel Installation UK: What to Expect on the Day

TLDR: Solar installation for a typical 10-16 panel system takes 1-2 days. Scaffolding is erected the day before. The crew installs mounting rails, panels, inverter, and electrical connections. Power is off for 1-2 hours during final connection to the consumer unit. A typical 4 kW system costs £5,000-£7,000 installed; larger 6-8 kW systems cost £7,000-£10,000. You can use the system once DNO notification is complete—usually within a week.

The day your solar panels get installed is genuinely exciting. After weeks of research, quotes, and paperwork, there's something satisfying about watching the crew transform your roof into a power station. But it's also natural to feel a bit apprehensive. What exactly happens? Will it damage your roof? How long will the power be off?

Having spoken with dozens of homeowners who've been through the process—and observed numerous installations myself—I can tell you that most people find it far less disruptive than expected. A good installer turns the whole thing into a surprisingly smooth operation.

This guide walks you through every stage: from the site survey weeks before, through installation day itself, to what happens after the crew leaves. By the end, you'll know exactly what to expect—and what questions to ask your installer.

Costs at a Glance

Before diving into the installation process, here's what you can expect to pay for a typical residential solar installation in the UK:

System SizeNumber of PanelsTypical CostAnnual GenerationBest For
3-4 kW8-10 panels£5,000-£7,0002,500-3,400 kWhSmaller homes, 2-3 bed
5-6 kW12-15 panels£6,500-£8,5004,200-5,100 kWhAverage homes, 3-4 bed
6-8 kW15-20 panels£8,000-£11,0005,100-6,800 kWhLarger homes, high usage
Add battery5-10 kWh£3,000-£6,000N/AMaximise self-consumption

These prices include scaffolding, installation, MCS certification, and DNO notification. VAT on residential solar is currently 0%, so the price you're quoted is the price you pay.

Real Homeowner Experiences

Michelle and Pete, Southampton (1990s detached): "We were nervous about getting solar—it felt like a big commitment. But the installation itself was the easy part. The scaffolding went up on Friday afternoon, and by Monday at 2pm, we had a working 5.4 kW system. The installers were really professional—they kept the noise down, cleaned up after themselves, and even explained how to use the monitoring app before they left. Total cost was £7,200 from Octopus Energy, and we're now generating about 4,500 kWh per year. Our electricity bill has dropped from £120/month to about £35."

Thomas, Birmingham (Victorian terrace): "I was worried about our older roof, but the surveyor checked everything thoroughly—went into the loft, examined the tiles, checked the rafters. He said it was fine but recommended they add some extra support brackets due to the slate tiles. On installation day, the crew of three arrived at 8am. They were drilling on the roof by 9, and by lunchtime, eight panels were up. The electrical work took the afternoon—they routed cables through the loft space down to the consumer unit in the kitchen. Power was off for about 90 minutes while they made the final connection. Total cost was £5,800 for a 3.2 kW system through British Gas Solar. Took about six hours start to finish."

Sarah, Cambridge (new build estate): "Our developer offered solar as an optional extra when we bought the house, but the price was ridiculous—£12,000 for what turned out to be a 4 kW system. We said no, then got quotes after moving in. Ended up paying £6,400 for a 4.4 kW system with a local MCS installer. The installation was textbook—scaffolding Monday, panels Tuesday, scaffolding down Wednesday. One thing nobody warned us about was the inverter noise. Ours is in the garage, and there's a quiet hum during the day when it's working. Not annoying, just unexpected. We're generating about 3,800 kWh per year and saving roughly £700 annually on electricity."

James and Carol, Edinburgh (stone-built bungalow): "Scottish weather meant our installation was rescheduled twice due to high winds. Third time lucky—a crisp, clear November day. The team from EDF Solar arrived at 8:30 with a van full of panels. Because we're a bungalow, the scaffolding was relatively simple—just around the south-facing side. By 4pm, we had 12 panels up and running. The whole thing cost £8,200 for a 4.8 kW system. We also added a 6 kWh battery for another £4,500, installed at the same time. The battery means we use about 85% of what we generate instead of exporting the surplus. On sunny summer days, we run entirely on solar from about 8am to 10pm."

Before Installation Day: The Lead-Up

2-6 Weeks Before: The Site Survey

Before any reputable installer commits to a quote, they'll conduct a detailed site survey. This isn't a quick look at your roof from the ground—expect it to take 30-60 minutes.

The surveyor will check:

After the survey, you'll receive a final quote and system design. This should include panel layout, expected generation figures, and any additional work needed (like consumer unit upgrades or structural reinforcement).

1-2 Weeks Before: Paperwork and DNO Notification

Your installer handles the paperwork, but here's what happens behind the scenes:

Day Before: Scaffolding Goes Up

Scaffolding erection typically takes 2-4 hours, depending on roof complexity. The scaffolding company will need access around the relevant sides of your house, so:

Scaffolding usually extends about 1.5 metres from the wall at ground level. It may block access to gates, side doors, or garden areas temporarily.

Installation Day 1: The Main Event

Morning (8:00-12:00)

The installation crew arrives early—typically 8:00-8:30. For a standard residential install, expect 2-4 people: usually one or two roofers/panel installers and one electrician.

First hour: Setup and safety

Next 2-3 hours: Roof work begins

This is the noisiest part—drilling into rafters makes considerable noise. If you work from home, plan for reduced concentration during the morning.

Afternoon (12:00-17:00)

Panel installation (1-2 hours for typical system):

Watching panels go up is surprisingly quick. Once the rails are in place, a 12-panel system can be mounted in 60-90 minutes.

Electrical work:

Power Outage

At some point during the electrical work, the installer needs to connect to your consumer unit. This requires shutting off your mains power—typically for 1-2 hours.

Plan ahead:

Installation Day 2 (If Needed)

Many installations complete in a single long day. However, some situations require a second day:

If work extends to day two, the system usually isn't operational until electrical commissioning is complete. Your power will be back on overnight between days.

What You Need to Do

Before Installation

On the Day

After Installation: Commissioning and Handover

Same Day

Once installation is complete, the installer will:

Following Days

Potential Issues and How They're Handled

Weather Delays

Heavy rain, high winds, or snow can delay roof work for safety reasons. Installers won't risk working in dangerous conditions—and you wouldn't want them to. If weather forces a postponement, they'll reschedule as soon as conditions improve.

Unexpected Roof Problems

Occasionally, the installation team discovers issues not visible during the survey—hidden rot, damaged rafters, or structural weaknesses. Good installers will stop work and discuss options with you rather than proceeding unsafely. This might mean additional costs for repairs before continuing.

Inverter Placement Changes

Sometimes the planned inverter location doesn't work once the team sees the actual cable routes. Be prepared for discussion about alternative locations—the installer should explain the trade-offs.

Consumer Unit Upgrades

Older consumer units may not have space for the solar circuit or may need upgrading to meet current regulations. This should ideally be identified at survey stage, but occasionally discoveries are made on installation day. A consumer unit upgrade typically adds £300-£500 to the cost.

Q&A: Installation Day

Q: Will the installation damage my roof?

A: A proper installation shouldn't cause any damage. Mounting brackets are fixed through the tile into rafters (the strongest point), and each penetration is sealed with flashing or weatherproof boots. Reputable MCS installers guarantee their workmanship and will return to fix any leaks that occur.

Q: What if it rains during installation?

A: Light drizzle usually doesn't stop work—installers are used to British weather. Heavy rain or high winds will delay roof work for safety. If the forecast looks bad, installers may postpone rather than start a job they can't finish.

Q: Can I watch the installation?

A: From a safe distance, absolutely. Many homeowners find it fascinating to see their panels go up. Just stay clear of the work area, don't climb scaffolding, and don't distract the team with constant questions—save those for the handover.

Q: How noisy is it?

A: The noisiest part is drilling mounting brackets into the roof rafters—comparable to other building work. Expect 1-2 hours of significant drilling noise, typically in the morning. The rest of the installation is relatively quiet.

Q: What about my loft insulation?

A: Cables typically run through the loft space. The electrician may need to move insulation temporarily and should put it back afterwards. Check after they've finished—occasionally insulation doesn't get replaced properly.

Q: Do I need to inform my insurance company?

A: Yes, you should notify your home insurance provider. Most standard policies cover solar panels without additional premium, but your insurer needs to know they're there. Get confirmation in writing.

The Bottom Line

Solar panel installation is one of those rare home improvements that's genuinely less disruptive than you'd expect. A professional crew can transform your roof into a clean energy generator in one or two days, with minimal mess and just a brief power interruption.

The key to a smooth installation is choosing the right installer. Look for MCS certification (essential for SEG eligibility), check reviews, and get at least three quotes. A good installer communicates clearly, handles all the paperwork, and leaves you with a working system and the knowledge to use it.

Most homeowners describe a sense of quiet satisfaction watching those first kilowatts appear on the monitoring app. After all the research and decisions, you've done something concrete to reduce your energy bills and carbon footprint. That's worth celebrating—preferably with a cup of tea made from solar-generated electricity.